Programme outcome
Started 14 May 2013 · odour observation: 2–4 days
Odour across the main site · observations during the first 2–4 days
Initial situation
The sludge bed received raw and activated sludge. The programme addressed accumulated organic matter and biological treatment.
Actions taken
Application began on 14 May 2013. The site and its facilities were photographed in May and June.
Application results
According to observations reported by the company, odour across the main site became almost imperceptible within 2–4 days. It remained noticeable in the wastewater receiving area.
Site and period
Within 2–4 days, odour was almost imperceptible across the main site; it remained noticeable in the wastewater receiving area. The photographs show facility conditions in May and June 2013.
Site photographs


Documentary basis
RASTR publication dated 16 June 2013 and photographs from the same programme. This is a separate facility from the historical 2012–2013 wastewater case.